About HALO / Timeline     23 Jul 2009
 
  

Timeline 2000-2009

2009 January 24: Arrival of HALO in Oberpfaffenhofen
February / March: Ground vibration test of HALO
August: test integration of user instrumentation
August to November: flight testing
December: Maintenance
2008 Flight test at Gulfstream
Interior & completion
FAA & LBA certification
2007 Modification of aircraft at RUAG
December: ferry aircraft to Gulfstream
2006 Wing Modification at GAC
April: Delivery of the aircraft to RUAG at Oberpfaffenhofen, start modification of aircraft at RUAG
2005 February: contract award to Gulfstream
November: completion of the green aircraft
2004 September: The Federal Ministry of Education and Research approves the HALO project
2003 April: Release of request for proposal for the HALO aircraft
2002 July: Statement of the Wissenschaftsrat (WR) on large scale facilities for basic scientific research - WR recommends the funding of HALO
2001 February: submission of the HALO proposal to the Federal Ministry of Education and Research
Evaluation of the proposal by the Wissenschaftsrat (Advisory Body for Science Policy)
2000 May: initiation of the HALO project by a meeting of the german atmospheric science community